Simulation-Based Validation of an Integrated 4D/5D Digital-Twin Framework for Predictive Construction Control
2511.03684v1
cs.CE, cs.AI, cs.LG, cs.SY, eess.SY
2025-11-08
Авторы:
Atena Khoshkonesh, Mohsen Mohammadagha, Navid Ebrahimi
Abstract
Persistent cost and schedule deviations remain a major challenge in the U.S.
construction industry, revealing the limitations of deterministic CPM and
static document-based estimating. This study presents an integrated 4D/5D
digital-twin framework that couples Building Information Modeling (BIM) with
natural-language processing (NLP)-based cost mapping, computer-vision
(CV)-driven progress measurement, Bayesian probabilistic CPM updating, and
deep-reinforcement-learning (DRL) resource-leveling. A nine-month case
implementation on a Dallas-Fort Worth mid-rise project demonstrated measurable
gains in accuracy and efficiency: 43% reduction in estimating labor, 6%
reduction in overtime, and 30% project-buffer utilization, while maintaining an
on-time finish at 128 days within P50-P80 confidence bounds. The digital-twin
sandbox also enabled real-time "what-if" forecasting and traceable
cost-schedule alignment through a 5D knowledge graph. Findings confirm that
integrating AI-based analytics with probabilistic CPM and DRL enhances
forecasting precision, transparency, and control resilience. The validated
workflow establishes a practical pathway toward predictive, adaptive, and
auditable construction management.